Removing bottleneck in public investment

Anh Nhi

Problems in site clearance were behind delays at nearly 60 per cent of public investment projects that fell behind schedule last year. Separating the site clearance and resettlement process from investment projects is considered an important solution in removing this long-lasting bottleneck that slows down public investment.